Surface Preparation for Fire Protection

The Foundation of Every Compliant Fire-Protection System

Surface preparation is the critical first stage in any intumescent fire-protection system. The condition of the substrate directly determines adhesion, coating build, durability and verified fire performance. Without correct preparation, even the highest-performing products will fail to meet their tested fire rating.
Close-up of a steel beam with rust and flaking paint under a concrete surface.
Substrate Condition Importance

Why Substrate Condition Determines System Performance

Structural steel must be clean, sound and properly prepared before any primer or intumescent coating is applied. Contamination, corrosion or weak underlying coatings prevent adhesion, compromise Wet Film Thickness accuracy and undermine fire-rating compliance. Correct preparation ensures the system performs exactly as tested and certified.
Correct Method

Selecting the Correct Preparation Method

The appropriate preparation method is determined by substrate condition, contamination type and project requirements.
Use Dry Ice Blasting When
Existing coatings are failing or contaminated and the substrate must be preserved without abrasive damage.
Use Shot / Grit Blasting When
Heavy corrosion, mill scale or rust is present and a clean steel profile is required to meet specification.
Use Mechanical Abrasion When
Sound coatings require roughening or preparation is limited to localised areas.
Use Cleaning & Degreasing When
Surfaces are fundamentally sound but require final removal of contaminants before coating application.
Compliance

Compliance & Environmental Controls

Surface preparation must align not only with cleanliness requirements, but also with environmental conditions and fire-rating system specifications.

Humidity Control

Moisture inhibits adhesion and traps contaminants. Preparation is carried out in controlled conditions, typically below 85% relative humidity.

Corrosion Management

Active corrosion must be fully removed. Any bare steel exposed during preparation is spot-primed immediately to prevent flash rust.

Mill Scale Removal

Mill scale is brittle and non-adherent and must be removed by abrasive blasting to SA 2.5 to achieve reliable coating adhesion.

Contamination Elimination

Oil, grease, dust and salts must be fully removed. Residual contamination compromises adhesion and can cause system failure under fire exposure.

Surface Preparation Methods for Structural Steel

Different substrate conditions require different preparation techniques. We assess corrosion levels, existing coatings and site constraints to specify the most appropriate method for compliance and long-term performance.
All Prep Methods
Graco 695 XT airless sprayer with a yellow bucket in an unfinished industrial interior with metal framing and construction equipment.
Hand in black glove holding a blue infrared thermometer showing 20.1°C and a black temperature and humidity meter showing 18.5°C, 73.2% relative humidity, and 13.6°C dew point.
Interior construction site with yellow steel support beams surrounded by red safety barriers and exposed ceiling ducts and wiring.
Featured Projects

Steel Fire Protection Delivered

Representative projects demonstrating our methodology across sectors and steel types.
From the founder

“After a decade in the protective coatings industry, I built FireCoatings to deliver compliant fire protection without unnecessary noise — just clear documentation, a controlled application process, and professional site practice.”

Myles Howson
Managing Director
eyebrow
"Thank you Myles and team for all your hard work on this one. It wasn't easy working around the schedule but you got it done without causing any further issues. It was a pleasure to work with you."
Chris
Project Manager, Millcroft Services
Interior view of a construction site featuring steel beams and columns painted with white protective coating and temporary support props.
eyebrow
"NuColour worked efficiently around our programme and delivered a on time at late notice. The team were organised, flexible, and professional throughout the works."
Ciprian
Site Manager, Principal Contractor – GEMCO
Close-up of a bright yellow structural steel column with rivets installed on a construction site indoors.
location index

Areas We Cover

NuColour delivers specialist contracting services across London and the surrounding regions. Our teams operate throughout the South East, supporting commercial, industrial, and large-scale refurbishment projects with consistent standards, professional oversight, and experienced delivery.